Keep up to date with how projects are going, and understand the process so far. New events will be added as the project progresses.

4 October 2018 Construction to start

Construction is expected to start on the top section of Constable Street and on Rongotai Road on Monday 15 October.

Contractors will move on to Crawford Road later in October. More details will be posted shortly.

19 April 2018 Councillors to consider Evans Bay Parade (Kilbirnie) proposals More Less

Councillors will consider the proposals for Evans Bay Parade (Kilbirnie) at a meeting of the City Strategy Committee on 19 April.

19 April 2018 Evans Bay Parade (Kilbirnie) proposals approved by Councillors

Councillors on the City Strategy Committee approved plans for the new Kilbirnie bus hub and a two-way bike path on Evans Bay Parade in Kilbirnie.

The behind-the-scenes work - which includes detailed design, preparing construction drawings, and teeing up contractors who are in high demand - all takes time. We expect construction on the two-way bike path to start in late 2018.

 

5 April 2018 Opportunity to observe group discussions More Less

In February/March this year, Wellington City Council sought feedback on traffic changes (resolutions) required to develop bike paths and lanes on parts of Oriental Parade, Evans Bay Parade (Kilbirnie), and Thorndon Quay.

People who provided feedback and requested the opportunity to speak with Councillors will provide their oral submissions in group discussions at Wellington Central Library on Thursday 5 April in two sessions at 5pm and 6.30pm.

A gallery with limited seating will be available for any members of the public who would like to come along to observe the group discussions but not take part themselves.

19 March 2018: Consultation closes on Evans Bay Parade (Kilbirnie section) and traffic and parking changes for the proposed new bus hub